However, ignoring the BS that explo-cos spout about their project being great because in reality, most aren't.
The CAPEX for a decent sized porphyry (or any large scale mine) typically run into the billions. No junior company can ever develop them, and so the best that they can do is entice a major to fund the project beyond the resource drilling stage.
However, ignoring the FOMO-mania that happens when metal prices go crazy, in general, most mining companies like to focus on projects that can support a minimum production profile, for example:
- 100,000 tonnes of copper or 100,000 ounces of gold a year for >10 years
The idea is that the project will pay back the CAPEX (a novel idea), produce lots of cash for many years.
Here is a nice chart from the USGS (link) that displaying CuEq% grade vs tonnage for various copper deposits. Porphyries sit towards the large but low grade end of the spectrum. I've added some annotations and some well known projects.
Remember: this chart uses the total resources for a project. Many projects have a high-grade core or are a combination of heap leach oxide and higher grade sulfide ores (with economics and cut-offs).
Smaller and/or lower grade projects do get developed, but often they are brownfield projects adjacent to an operation that mined a neighboring higher grade deposit.
What you want is:
Here is a nice chart from the USGS (link) that displaying CuEq% grade vs tonnage for various copper deposits. Porphyries sit towards the large but low grade end of the spectrum. I've added some annotations and some well known projects.
| blue crosses = porphyry projects |
Remember: this chart uses the total resources for a project. Many projects have a high-grade core or are a combination of heap leach oxide and higher grade sulfide ores (with economics and cut-offs).
Smaller and/or lower grade projects do get developed, but often they are brownfield projects adjacent to an operation that mined a neighboring higher grade deposit.
What you want is:
- A project that is in the top right part of the chart = takeover target
- An exploration stage project that shows the potential to get into the top right area.
What you want to look for are projects that are a decent size >200Mt and a reasonable grade - around 0.6% CuEq or >1 g/t AuEq, or show the potential to get there.
However, grade and tonnes aren't the only factors that impact a project's economics, but it is a good starting point.